Additional feature that enables resource planning based on the assignment of users to phases
This application is an Additional Feature. You can find the corresponding config set here.
As an alternative to normal resource planning, it is also possible to plan for the assignment of users to the phases (so-called User-phase-links).
In the System settings under resource planning, this additional feature creates the property Resource planning type with conversion from Standard to User-phase-allocation.

Resource planning is then based on the assignment of users to phases:

Start date and End date.Start date and End date on project phases take into account the data of all user allocations, analogous to the activity assignments.Start date and End date on the phase can be overwritten by individual information on the phase-users-link. However, it is mandatory to specify a start and end date.An effort budget is set on the allocation of an user to a phase. In this example, Lars Sorenson is scheduled for 120 hours for the introduction phase from 01.09.2025 to 31.12.2025 and Judith Feller for 100 hours in the individual period from 01.09.2025 to 31.12.2025.
In the resource planning view, you can see the distribution on the phase:

The following rules apply:
Important information before importing can be found in the article Interesting facts about the additional features. Please note that config sets change data in Vertec, which may result in existing data being overwritten.
The exact import process can be found in the Articles about the config sets.
Download the additional feature with the following link:
| Version Requirement | Download |
|---|---|
| 6.7.0.16 | ConfigSet_RessourcePlanningUserPhaseLinks.xml |